If you are planning to obtain Microsoft Project certification of Microsoft 74-343 exam, you need to employ serious and solid efforts on your part. Microsoft Certification have strict criterion of evaluation. The candidates for MS Project Exam 74-343 Exam Prep are required to have full command on all the aspects of the Microsoft certification. The internet can prove a great help to you to prepare yourself for the Killtest MS Project Exam 74-343 Exam Prep. Killtest Microsoft technical experts have collected and certified questions and answers of MS Project Exam 74-343 Exam Prep which are designed to cover the knowledge points of the Microsoft 74-343 exam and enhance candidates’ abilities. Killtest 74-343 test questions are designed by highly experienced and certified trainers that have gathered the best 74-343 exam questions and answers that will Guarantee success on the Killtest MS Project Exam 74-343 Exam Prep. With Killtest MS Project Exam 74-343 Exam Prep, you can pass the Microsoft Project 74-343 exam easily, get the Microsoft and go further on Microsoft career path.

74-343 Managing Projects with Microsoft Project 2013 Test Questions 2017

You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies.To investigate the status of the critical path, you insert the Total Slack column into a task table.You discover that many of the tasks have negative Total Slack values.
You need to resolve the negative Total Slack values.What should you do?
A.Re-assign resources that have more availability at the time of the negative slack.
B.Remove lag time from task relationships.
C.Remove as many constraints as possible.
D.Remove lead time from the task relationships.
Answer: C

Youare a project manager who uses Project Professional 2013.You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013.You use milestones as key deliverables, and you use summary tasks as phases.Yourcompany requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.Youneed to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.Whatshould you do?
A.Addall summary tasks to your timeline.ProjectProfessional2013 will automatically recognize and add all milestones on each stage toyour Timeline view.Copy the full-sizetimeline andpaste to thePowerPoint slide.
B.Addall summary tasks to your timeline.Addall milestones to your timeline.Copy the full-sizetimeline and paste to your PowerPoint slide.
C.Create a new Timeline viewfrom existing tasksin your project plan.Drag the timeline into a blank PowerPoint slide.
D.Create a new Timeline view that automatically shows milestonesforeachstage of your project.Copy the full-sizetimeline and paste to your PowerPoint slide.
Answer: B

You are a project manager who uses Project Professional 2013.You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013.You use milestones as key deliverables, and you use summary tasks as phases.Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.What should you do?
A.Add all summary tasks to your timeline.Project Professional 2013 will automatically recognize and add all milestones on each stage to your Timeline view.Copy the full-size timeline and paste to the PowerPoint slide.
B.Add all summary tasks to your timeline.Add all milestones to your timeline.Copy the full-size timeline and paste to your PowerPoint slide.
C.Create a new Timeline view from existing tasks in your project plan.Drag the timeline into a blank PowerPoint slide.
D.Create a new Timeline view that automatically shows milestones for each stage of your project.Copy the full-size timeline and paste to your PowerPoint slide.
Answer: B

The 74-343 Managing Projects with Microsoft Project 2013 has turned into so renowned that a huge number of participants are considering getting success in it in order to attain success in a particular area in the arena of Information Technology. Killtest MS Project Exam 74-343 Exam Prep have such a fabulous worth as it helps contestants to achieve maximum level of employments in renowned IT firms in their specific area of interest. Before you make your decision to buy Killtest MS Project Exam 74-343 Exam Prep, you can have a try on the free demo. In this way, you can know the quality of Killtest 74-343 practice exam and make your best choice. Microsoft 74-343 exam require hands-on experience and working knowledge about the 74-343 product, it is highly recommended that you use the MS Project Exam 74-343 Exam Prep provided by Killtest to help you get high score on 74-343 Managing Projects with Microsoft Project 2013 exam. 74-343 practice questions are built with full coverage of all exam objectives in a systematic approach.

Killtest is the best catalyst to help IT personage be successful. Many people who have passed some IT related certification exams used Killtest 74-343 practice exam. Killtest expert team use their experience for many people participating in Microsoft certification 74-343 exam to develope the latest effective MS Project Exam 74-343 Exam Prep, which include real Microsoft 74-343 questions and answers. The MS Project Exam 74-343 Exam Prep covering a wide range, not only to improve your knowledge of the culture, the more you can improve the operation level. As usual, with every purchase of Microsoft 74-343 practice exam, you will receive the 74-343 questions and answers in 2 formats, PDF and Testing Engine. But for some special products, Killtest only provides the Testing Engine.

Posted in Microsoft.

Tagged with , , , , .


0 Responses

Stay in touch with the conversation, subscribe to the RSS feed for comments on this post.



Some HTML is OK

or, reply to this post via trackback.

Spam Protection by WP-SpamFree